An old bathroom may no longer fit into your needs and lifestyle. Upgrading can give the existing setup a complete makeover. From adding new sanitaryware for aesthetics to improving organisation with shelves and cabinets, you can easily turn the space into a spa-like retreat.

With new concepts emerging, homeowners can choose cutting-edge showers, bathtubs, floor fixtures, and newer toilet models. However, before the remodeling work begins, you may wonder how much time a typical washroom refit takes. Professional bathroom fitters in Plymouth can incorporate all the changes you want without a major structural overhaul.

How Long Does a Standard Bathroom Refit Take?

A simple upgrade takes little time. Expect around 3 to 5 days to complete the work. For a complete refurbishment, keep aside 3 weeks or more. The whole timescale depends on several factors:

  • Size of the washroom
  • Kind of work you need, both electrical and plumbing
  • Alterations to the bathroom’s existing design
  • Type of sanitaryware, bathtub and shower you choose

Bathroom Refitting: A Day-by-Day Timeline

A standard refurbishment process has many intricacies. Here’s what you can expect.

Day 1: Removing the Old Fixtures

The first day of renovation focuses on preparing the space. The skilled team of bathroom fitters in Plymouth removes the shower, bathtub, toilet, basin, and sanitaryware. They may also take out the existing tiles if you’re looking to install new floor materials.

Days 2–3: Doing the Various Plumbing and Electrical Work

On days 2 and 3, drainage and pipework work and new light installations begin in full swing. While working, the experts follow safety requirements to keep the work uninterrupted.

Day 4: Preparing and Waterproofing the Walls

Bathroom renovation projects often involve installing new tiles. For this, the walls and the floors need proper preparation. Damaged areas get special attention. Uneven surfaces are levelled.

This is important to set up new tiles and make them durable. Rubber- or plastic-based waterproofing liquid is installed, and silicone sealants and primers are applied to make the floors and walls moisture-resistant.

Days 5–7: Inserting Appropriate Flooring Materials

Tiling often takes up most of the timescale in a bathroom renovation project. The expert team sets up wall and floor tiles according to the design you suggested.

Both ornamental patterns and simple tiles can give your space a striking finish. Tiling is followed by grouting and is often done when the flooring surface is prepared.

Days 8–9: Setting Up the New Bathroom Fixtures

During this time, you can expect the new bathroom suite to be installed. This can include the bathtub, shower screens, wash basin, sanitaryware, and more. The plumber ensures a steady water supply. The lighting and ventilation fittings are also set up accurately.

Collaborate with Professional Fitters For a Seamless Work

A bathroom refurbishment is complex and often involves several stages. Every stage needs careful planning, which only experts can do. The result is a flawless final installation that surpasses expectations.

At CLS Construction SW, we excel in top-notch bathroom fitting in Plymouth. We bring two decades of expertise in full bathroom refurbishments and remodelling.

Our experienced team focuses on quality work and reasonable pricing. We also streamline the design planning process by blending visual appeal with functionality.